When engineers have decided where the well and tower will be situated we will post pictures of what the area looks like at the moment. And we hope, not too long after that, we will be able to start showing you how the work is going.
Total Project Cost - £ 8000
​​
We understand donors need to be certain every penny they give goes to the project.
Donations will go through the gofundme page to the Brue Valley Rotary Club charity account. Its sister club in Stone Town Zanzibar will make payments to the local contractors.
​
We have costed the project in four stages and, as the money for each stage becomes available, work will start and pictures be posted regularly, here and on our gofundme page, so donors can see exactly what is being achieved. (The stage costs are rounded up and allow for exchange rate fluctuations.)
​
​
Stage One. To dig and connect the well:-
-
Dig process
-
Water Pump
-
Hose pipe
-
Wire and its insulators
-
Ditch (from well to tower and then to toilets
-
Electrician
Total 6,000,000Tzs £2000
​
Stage Two. To buy the storage tank and erect the tower:
-
Storage tank
-
Sand 1 Lorry (10 tones)
-
Concrete bricks -
-
Grit boxes
-
Cement bags
-
Contractors
Total 6,000,000Tzs £2000
​
Stage 3. To buy toilet bowls, taps and plumbing requirements (pipes, joints, etc) and install them :
-
Toilet bowls and basins -
-
Taps and sanitation materials
-
Contractors
Total 6,000,000Tzs £2000
Stage Four. To buy tiles and refurbish the toilet blocks:
-
Wall tiles
-
Floor tiles
-
Sand
-
Contractors
Total 6,000,000Tzs £2000
​
​
​